10 Craig St, Brantford
Part2- This part was to construct two foundation pads for the WWTP main tanks. The works covered by Eyeco Inc. in this part were to excavate the existing soil from the ground level up to the needed elevation, and to supply, place, and compact granular materials on the excavated surface, supply and pour a lean concrete layer on the compacted granular layer, supply and install rebars and dowel bars with different shapes and sizes, supply and execute formworks and falseworks, as well as to supply, pour, consolidate, finish, cure, and protect concrete for the tanks’ foundation pads. In this part, there was no major challenge, but the execution of a huge volume of work in a very limited time based on the project timeline.